Eastmark Aquatic Complex: Mesa Council to Vote on First Construction Contract August 31

District 6 residents will get their first real answer on the neighborhood pool they were promised at the community's founding

A young girl in a neon yellow bikini runs laughing through ground-level water jets at an outdoor splash pad surrounded by palm trees and red shade sails, with another child visible in the background
A splash pad like the one currently at Eastmark Great Park — the proposed aquatic complex would replace this type of facility with a full pool complex for southeast Mesa residents. (InsideTheValley.com)

The short version

  • Sun Eagle Corporation's pre-construction contract is $136,295 — its main deliverable is a Guaranteed Maximum Price.
  • Mesa's 2024 bond earmarked $67.2 million across 2 aquatics facilities; a designer was already hired before this vote.
  • The project is in District 6, funded by the $170 million Parks and Culture GO Bond approved November 2024.
  • Sun Eagle Corporation is a Chandler-based contractor in business since 1978 and certified as an SDVOSB.
  • Eastmark Great Park is a city-owned public park planned to reach 96 acres in southeast Mesa.

Yes, Mesa is building a public aquatic complex in Eastmark. On August 31, 2026, the Mesa City Council is scheduled to vote on awarding Sun Eagle Corporation a $136,295 pre-construction services contract for the Eastmark Aquatic Complex — project code CP0756SEAQ. If approved, it marks the first concrete construction step toward a full pool facility for southeast Mesa’s District 6 residents.

You have been driving to central Mesa for a public pool — that changes here

If you live in Eastmark or the surrounding southeast Mesa neighborhoods, you already know the math. The nearest public pools are concentrated in central and north Mesa. On a summer afternoon when the concrete hits 110 degrees, that drive is real, and it is a trip Eastmark families have been making since the community opened.

The aquatic complex will sit inside Eastmark Great Park, the city-owned public park north of Ray Road and west of Eastmark Parkway. This is not an HOA amenity — it belongs to the city, open to all Mesa residents. The complex replaces the existing splash pad with a full aquatic facility.

Eastmark was founded with a promise. The original masterplan called for a potential aquatic center alongside recreational fitness facilities, lit fields, and school sites. Residents have waited through years of growth, paid Community Facilities District assessments toward Great Park development, and watched the community fill in around an amenity that never quite arrived. The August 31 vote is the turning point that makes that wait tangible.

What Mesa City Council is voting on August 31

City staff recommend awarding a Construction Manager at Risk — CMAR — pre-construction services contract to Sun Eagle Corporation in the amount of $136,295. The project code is CP0756SEAQ.

Pre-construction is not construction. Think of it as hiring an expert to figure out exactly what the project will cost and how to build it before anyone breaks ground. The scope includes design constructability review, cost estimating, construction sequencing, and phasing plans. The primary deliverable is a Guaranteed Maximum Price — a GMP — which sets the ceiling on what taxpayers will pay for construction.

The GMP is the number to watch. Once it is set, Mesa and the public will know the full cost of the aquatic complex and can plan the construction timeline around it. Nothing about the final build price is known yet — that is the point of this phase.

City Council has final decision authority. Staff recommend approval; council decides.

Interior of a large commercial building under construction showing concrete masonry walls, exposed steel roof trusses, a concrete slab floor, scissor lifts, and a worker in a high-visibility vest walking through the open structure

A construction site similar in scale and structure to what pre-construction planning manages: CMU walls, steel trusses, and open slab — the kind of complexity a CMAR contractor prices and sequences before a single bid goes out. (InsideTheValley.com)

Meet Sun Eagle Corporation, the Chandler veteran-owned firm recommended for the job

Sun Eagle Corporation is based at 461 N Dean Avenue in Chandler — a few miles from the project site. The company has been in business since 1978 and is family-owned. It holds federal certification as a Service-Disabled Veteran-Owned Small Business.

The firm has completed more than 386 projects totaling over $1.7 billion in construction value. Aquatic centers are listed among its completed building types. This is not a company new to pool facilities or to the Phoenix Valley.

How the 2024 Mesa GO bond pays for this

Mesa voters approved a $260 million General Obligation Bond package in November 2024. The vote was certified. Of that total, $170 million was directed toward recreation, educational, and cultural facilities. The Eastmark Aquatic Complex is funded from that pot.

The 2024 bond package set aside $67.2 million across two new aquatics facilities. A designer was already hired for the Southeast Aquatics Facility — which aligns with the Eastmark project — before this CMAR contract came to council. That means design work is already moving. The August 31 vote brings the construction management side of the team on board to work alongside the designer during pre-construction.

GO bonds are repaid by property taxes. Mesa voters said yes. Now the city is executing.

Where the aquatic complex will be located

The Eastmark Aquatic Complex will be located at Eastmark Great Park. The park is owned and operated by the City of Mesa — not a homeowners association or private developer. It sits north of Ray Road and west of Eastmark Parkway in southeast Mesa. The park is planned to grow to 96 acres.

The aquatic complex replaces the existing splash pad at the park. District 6 covers this area of the city.

The August 31 vote and what follows it

The Mesa City Council hears this item on August 31, 2026. If council approves the contract, Sun Eagle Corporation begins pre-construction services. The team works through design review, cost estimating, sequencing, and phasing. At the end of that process, the city receives a Guaranteed Maximum Price.

That GMP — not yet known — is when the full construction cost becomes public and a build schedule can be set. Construction timing depends on what the GMP process reveals. No construction start date or completion date has been established from the verified record. Watch for the GMP as the next major milestone after an August 31 approval.

Common questions

Is Mesa really building a pool in Eastmark?

Yes. The City of Mesa is moving forward with the Eastmark Aquatic Complex, project code CP0756SEAQ, funded by the 2024 Parks and Culture General Obligation Bond. The August 31, 2026 council vote on a pre-construction services contract is the first concrete construction step.

What is the Mesa City Council voting on August 31, 2026?

Council is voting on whether to award Sun Eagle Corporation a $136,295 CMAR pre-construction services contract for the Eastmark Aquatic Complex. The scope covers design review, cost estimating, construction sequencing, phasing plans, and development of a Guaranteed Maximum Price. Staff recommend approval; council has final say.

What is a CMAR contract and why does it matter for the Eastmark pool?

CMAR stands for Construction Manager at Risk. The contractor works alongside the designer during pre-construction to review plans for buildability, estimate costs, and develop a Guaranteed Maximum Price — a firm cost ceiling for taxpayers. It is a common method for large public facilities. This pre-construction phase comes before any dirt is moved.

What is a Guaranteed Maximum Price (GMP) and when will we know the final cost?

The GMP is the contractual cap on what the construction will cost. It is the primary deliverable of the pre-construction services phase. The GMP has not been set yet — producing it is the purpose of the $136,295 contract being voted on August 31. Once established, it will give the public and the city a firm number.

How is the Eastmark aquatic center being paid for?

The project is funded by Mesa’s 2024 Parks and Culture General Obligation Bond. Mesa voters approved a $260 million GO bond in November 2024 — $170 million of which went to recreation, educational, and cultural facilities. The bond package earmarked $67.2 million across two new aquatics facilities, including the southeast Mesa location.

Where exactly will the Eastmark Aquatic Complex be located?

The complex will be located at Eastmark Great Park, a city-owned public park north of Ray Road and west of Eastmark Parkway in southeast Mesa. The park is planned to grow to 96 acres. The aquatic facility will replace the existing splash pad at the park.

Who is building the Eastmark Aquatic Complex?

City staff recommend Sun Eagle Corporation, a Chandler-based family-owned contractor at 461 N Dean Avenue, for the pre-construction services phase. The company has been in business since 1978, is certified as a Service-Disabled Veteran-Owned Small Business, and has completed over 386 projects including aquatic centers.

Was an Eastmark pool promised to residents from the beginning?

Yes. The original Eastmark masterplan called for a potential aquatic center as part of Eastmark Great Park, along with recreational fitness facilities, lit fields, and school sites. Residents have paid Community Facilities District assessments toward Great Park development while waiting for the aquatic center to materialize.

When will the Eastmark aquatic center be built?

No construction start date or completion date has been established in the public record. The next step is establishing a Guaranteed Maximum Price during the pre-construction phase. That GMP will set the foundation for a construction timeline. The August 31, 2026 council vote on the pre-construction contract is the immediate milestone.

Aaron Dotterer
Aaron Dotterer
REALTOR® · Dott Real Estate Group, Real Broker

Firefighter-EMT and licensed REALTOR® living in Eastmark. I cover what actually changes for residents when the Valley builds.

Book a strategy call
★★★★★
He was patient and understanding and never pressured us into a house or area. He listened to us as we explained our needs and wants…
— Maggie
★★★★★
Aaron was very helpful and supportive when it came to finding a home. He was quick to respond and was ready to help wherever he could…
— Amanda
★★★★★
Responsive, organized, and never made us feel like just another transaction. Highly recommend.
— John

Sources