Intel Fab 62 Chandler: Sixth Factory Targets Operations by End of 2028

Chandler's newest chip factory is moving from shell to working fab — and thousands of high-wage jobs follow

Aerial drone photograph of Intel's Ocotillo semiconductor campus in Chandler, Arizona, showing large industrial fabrication buildings with rooftop mechanical equipment, a distinctive curved-facade entry structure in the foreground, and flat desert suburban sprawl with dry mountains on the horizon under clear blue sky.
Intel's Ocotillo campus in Chandler, Arizona — home to six high-volume semiconductor manufacturing facilities once Fab 62 reaches operations by end of 2028. (Intel)

The short version

  • Intel's $32 billion two-fab Arizona investment was originally promised production-ready by 2024 — now targeting late 2028.
  • Fab 62 will be Intel's 6th high-volume factory at the Ocotillo campus in Chandler.
  • The 2021 groundbreaking projected 3,000 high-tech jobs, 3,000 construction jobs, and 15,000 indirect community jobs.
  • Intel's existing Arizona operations generate an estimated $10.7 billion in annual economic impact.
  • Oct. 22, 2026: Intel's Naga Chandrasekaran confirmed tool installation underway — the first firm public timeline for Fab 62.

Intel is now installing production tools inside Fab 62 at its Ocotillo campus in Chandler. The company says the factory will be operational by end of 2028. It is the first time Intel has publicly committed to a firm timeline for the project. For East Valley residents, that means thousands of promised high-wage manufacturing jobs are roughly two years out.

If you live near Ocotillo, here is where things actually stand

The construction you see around the Price Road corridor is real and accelerating. Intel has finished the Fab 62 building shell. Now workers are installing the specialized production equipment inside. That step is what turns a large industrial building into a working chip factory.

But the high-wage manufacturing jobs are still more than two years away. Right now the area gets sustained construction-phase employment, heavy equipment traffic, and active supplier and vendor work. If you own or rent near Ocotillo, that activity supports local home values and rental demand today. The bigger economic wave — thousands of full-time, high-paying manufacturing positions — comes after the factory opens.

There is an honest tension worth naming. Intel and then-Governor Doug Ducey broke ground on Fab 52 and Fab 62 together on Sept. 24, 2021. At that ceremony the project carried a “production ready in 2024” promise. The current target is late 2028. That is a roughly four-year slip. East Valley residents and suppliers who planned around the original schedule deserve to see those two dates side by side.

What Intel Fab 62 is, and where it fits on the Ocotillo campus

Fab 62 will be the sixth high-volume manufacturing facility at Intel’s Ocotillo campus in Chandler. The fifth, Fab 52, is already operational. Fab 52 covers 2.9 million square feet and manufactures chips on Intel’s 18A process technology. Fab 62 adds a separate, dedicated factory to that campus footprint.

Intel has not officially assigned a specific process node to Fab 62. Based on Intel’s disclosed technology roadmap, it could potentially run Intel 18A, 18A-P, or 14A. Intel has not confirmed which one.

Aerial view of Fab 62 under construction in September 2026, showing large cleanroom roof structures with industrial piping and HVAC systems, an American flag on the front facade, and active construction areas in an arid desert-suburban landscape.

Fab 62 as it appeared in September 2026, with the building shell complete and construction equipment still active around the perimeter. (Intel / Tom’s Hardware)

From the 2021 groundbreaking to tool installation: the Fab 62 timeline

The Sept. 24, 2021, groundbreaking was a major public event. Then-CEO Pat Gelsinger called the combined investment the largest private investment in Arizona state history. Intel put the price tag for both new factories at $32 billion.

At that ceremony, both fabs were expected to be production-ready by 2024. Fab 52 reached operations first. Fab 62 now targets the end of 2028.

The person who confirmed that updated timeline was Naga Chandrasekaran, executive vice president and chief technology and operations officer of Intel Foundry. He published a company update on U.S. manufacturing investments on Oct. 22, 2026. That update was also the first time Intel publicly shared a firm construction timeline for Fab 62.

Intel-branded groundbreaking ceremony on a construction site stage with a speaker at an Intel podium, five executives seated, CAT excavators behind, and a large building bearing Arizona and US flags visible in the background.

The Sept. 24, 2021, groundbreaking for Fab 52 and Fab 62 at the Ocotillo campus featured then-Governor Doug Ducey and then-CEO Pat Gelsinger. Gelsinger described the $32 billion two-fab commitment as the largest private investment in Arizona history. (City of Chandler)

Intel’s $32 billion investment and its $10.7 billion annual Arizona footprint

The $32 billion figure covers Fab 52 and Fab 62 together. Intel’s existing Arizona presence already produces $10.7 billion in estimated annual economic impact. Intel has been manufacturing in Arizona for nearly half a century, making the state its longtime production home.

That existing footprint explains why Fab 62 is an expansion rather than a gamble. Suppliers, workforce pipelines, and infrastructure are already in place around Chandler.

Jobs: what the commitment says and when residents should expect hiring

The 2021 groundbreaking came with specific job projections tied to both fabs. Intel committed to more than 3,000 new high-tech, high-wage jobs. It also committed to 3,000 construction jobs. The expansion was estimated to support about 15,000 additional indirect jobs in the broader community.

Construction jobs are active now. High-tech manufacturing roles tied to Fab 62 depend on the factory reaching operations. With the target at end of 2028, direct manufacturing hiring is still more than two years out. Suppliers and vendors serving the campus will likely see increased activity before then.

Aerial drone photo at sunset of a large industrial semiconductor campus under active construction with multiple large yellow cranes and an American flag hanging from one crane, set against flat desert suburban sprawl and distant mountain silhouettes.

Active construction at the Ocotillo campus, with multiple cranes visible against the Phoenix metro skyline at sunset. The campus will eventually include 6 high-volume manufacturing facilities. (Intel)

End of 2028: what has to happen before Fab 62 starts running

Tool installation is underway. Semiconductor factories require precise equipment placement, calibration, and testing before a single chip can be made. Intel has not released a month-by-month schedule. End of 2028 is the most specific public target available.

Watch for continued heavy equipment activity around Ocotillo. Watch also for supplier contract announcements tied to the build-out. Intel has not publicly assigned a process node to Fab 62, so any update there would be significant.

Intel has not publicly tied a specific CHIPS and Science Act incentive dollar amount to Fab 62 alone. Arizona’s semiconductor ecosystem — anchored by Intel’s nearly fifty-year presence in Chandler — keeps drawing industry attention. For more on the Valley’s growing chip-industry footprint, see our guide to SEMICON West’s permanent move to Phoenix. You can also read our breakdown of TSMC’s Phoenix water use.

Common questions

When will Intel's Fab 62 in Chandler open?

Intel is targeting operations at Fab 62 by the end of 2028. Construction of the building shell is complete and production tool installation is now underway.

What is Intel Fab 62?

Fab 62 is Intel's sixth high-volume semiconductor manufacturing facility at its Ocotillo campus in Chandler, Arizona. The building shell is finished and Intel is currently installing production equipment inside.

Why is Fab 62 delayed — wasn't it supposed to open in 2024?

Yes. When Intel broke ground on Fab 52 and Fab 62 together on Sept. 24, 2021, both fabs were projected to be production-ready by 2024. The current target for Fab 62 is the end of 2028 — roughly a four-year slip from the original promise.

How many jobs will Intel Fab 62 create?

The combined two-fab expansion announced in 2021 was projected to create more than 3,000 high-tech, high-wage jobs and 3,000 construction jobs, while supporting an estimated 15,000 additional indirect community jobs. Construction jobs are active now; high-tech manufacturing hiring tied to Fab 62 depends on the factory reaching operations by end of 2028.

What chip process will Fab 62 make?

Intel has not officially assigned a specific process node to Fab 62. Based on Intel's disclosed technology roadmap, the factory could potentially run Intel 18A, 18A-P, or 14A — but Intel has not publicly confirmed which one.

How much is Intel investing in Arizona?

Intel describes its combined investment in Fab 52 and Fab 62 at $32 billion. Separately, Intel estimates its existing annual economic impact in Arizona at $10.7 billion.

What is the difference between Fab 52 and Fab 62?

Fab 52 is Intel's fifth high-volume factory at the Ocotillo campus and is already operational, manufacturing chips on Intel's 18A process technology in a 2.9 million square foot building. Fab 62 is the sixth factory on the same campus — the shell is built but it won't reach operations until the end of 2028.

Who announced the Fab 62 construction update?

Naga Chandrasekaran, executive vice president and chief technology and operations officer of Intel Foundry, confirmed construction and tool-installation progress in a company update on U.S. manufacturing investments published Oct. 22, 2026. It was the first time Intel publicly shared a firm timeline for Fab 62.

What does Intel Fab 62 mean for Chandler home values and real estate?

Construction-phase activity at Fab 62 supports ongoing jobs and supplier activity near the Ocotillo campus now, which tends to sustain housing demand in the surrounding area. The larger employment wave — thousands of high-wage manufacturing jobs — is tied to the factory reaching full operations, targeted for end of 2028.

What is Intel's economic impact in Arizona?

Intel estimates its annual economic impact in Arizona at $10.7 billion, reflecting its nearly half-century of manufacturing presence in the state and a broad network of local suppliers and service providers.

Aaron Dotterer
Aaron Dotterer
REALTOR® · Dott Real Estate Group, Real Broker

Firefighter-EMT and licensed REALTOR® living in Eastmark. I cover what actually changes for residents when the Valley builds.

Book a strategy call
★★★★★
He was patient and understanding and never pressured us into a house or area. He listened to us as we explained our needs and wants…
— Maggie
★★★★★
Aaron was very helpful and supportive when it came to finding a home. He was quick to respond and was ready to help wherever he could…
— Amanda
★★★★★
Responsive, organized, and never made us feel like just another transaction. Highly recommend.
— John

Sources

↑