Know What's Coming to Your Street

News

I-10 Wild Horse Pass Corridor Project: Segment 3 Is Under Construction Near Loop 202

South Valley commuters face years of construction near Loop two-oh-two as the longest stretch of a billion-dollar freeway project gets underway.

The short version

  • Segment 3 costs $410M and is the longest of the 4 segments, running 11 miles.
  • Coffman Specialties, Fisher Sand & Gravel, and Stantec are building segment 3.
  • HOV lanes added in both directions, but only between Loop 202 and Riggs Road.
  • A brand-new Koli Road interchange is included — not a reconstruction of an existing one.
  • The full 26-mile project wraps up by late 2029; segment 4 starts in 2027 or early 2028.

Construction is now active on the third segment of the I-10 Wild Horse Pass Corridor Project. The segment runs 11 miles between the Loop 202 (Santan/South Mountain Freeway) interchange and the Gila River. It is the longest of the four phases. If you drive I-10 south of Chandler toward Casa Grande, this project will affect your commute through 2029.

Your commute south of Chandler is changing for years — here is what to expect

Do you use I-10 to reach Casa Grande or points south from Ahwatukee, Chandler, or South Phoenix? This is the construction zone closest to you. It covers the most heavily traveled part of the corridor.

Lane closures and shifting traffic patterns near Loop 202 and Riggs Road will be routine. Active work at four interchanges runs through 2029. Expect disruption on weekday mornings and weekends.

The long-term payoff is real. You will gain a third general-purpose lane in both directions across all 11 miles. Between Loop 202 and Riggs Road, crews are also adding an HOV lane in each direction. If you carpool to work, that lane becomes yours once it opens.

The new Koli Road interchange will give drivers between Wild Horse Pass Boulevard and Queen Creek Road a direct access point that does not exist today.

Concrete pavement is replacing all the existing asphalt. Stantec says the concrete lasts about 30 years. The cost is nearly the same as new asphalt. Once crews finish, this stretch should not need major pavement work for decades.

Aerial drone photo of multi-lane I-10 at Wild Horse Pass crossing under an overpass in the Sonoran desert, with heavy traffic in both directions including semi-trucks.

Heavy truck and passenger traffic moves through the Wild Horse Pass corridor — the most heavily traveled stretch of the four-segment project. (InsideTheValley.com)

What the I-10 Wild Horse Pass Corridor Project actually is

The I-10 Wild Horse Pass Corridor Project is a nearly $1 billion widening program. It stretches 26 miles from Loop 202 in south Phoenix to State Route 387 near Casa Grande. ADOT divided the work into four segments to manage construction across Maricopa and Pinal counties.

The project replaces aging infrastructure, adds travel lanes, and installs modern safety technology. When all four segments are done, the full corridor will be wider, safer, and paved in concrete.

Every improvement coming to the 11-mile Loop 202–Gila River stretch

Here is what crews are building in segment 3:

  • A third general-purpose lane in both directions across the full 11 miles
  • An HOV lane in both directions between Loop 202 and Riggs Road — not the full 11 miles
  • Reconstruction of three existing interchanges: Wild Horse Pass Boulevard, Riggs Road, and Queen Creek Road/State Route 347
  • A brand-new interchange at Koli Road, between Wild Horse Pass Boulevard and Queen Creek Road/SR 347 — a new access point, not a rebuild
  • Full replacement of asphalt pavement with concrete, designed to last about 30 years
  • Overhead messaging boards, freeway cameras, and wrong-way detection systems installed throughout

Aerial view of a highway bridge crossing a dry desert wash with active construction equipment including excavators, stacked concrete beams, and live traffic along the Wild Horse Pass corridor.

Active construction equipment and staged materials visible along the Wild Horse Pass corridor during an earlier phase of work. (InsideTheValley.com)

Who is building it: the Coffman-Fisher joint venture

The design-build team for segment 3 is called Coffman-Fisher. It is a joint venture of three firms: Coffman Specialties, Inc., Fisher Sand & Gravel Company, and lead designer Stantec Consulting Services Inc. ADOT selected this team through a design-build procurement. The estimated value of segment 3 is $410 million.

Segment 1 — the Gila River bridge replacement — was built by Pulice Construction for $71.2 million. The cost difference reflects how much longer and more complex segment 3 is.

Night construction scene with workers in high-visibility vests operating a concrete vibrator over a large rebar reinforcement grid, with a yellow gantry crane visible in the background.

Night crews work a concrete pour on the Wild Horse Pass corridor — concrete pavement is replacing asphalt across all 11 miles of segment 3. (InsideTheValley.com)

All four segments: where each one stands right now

The 26-mile corridor is split into four segments. Here is where each stands:

  • Segment 1 — Gila River bridges: Built by Pulice Construction for $71.2 million. Construction started May 2024. Finishing touches on the new bridges were scheduled for completion around October 2026.
  • Segment 2 — Gas Line Road to near Pinal Avenue/SR 387: Covers about 10 miles in Pinal County near Casa Grande. Construction started January 2026 and is underway.
  • Segment 3 — Loop 202 to Gila River: The longest segment at 11 miles. Active construction started October 2026. Built by Coffman-Fisher ($410 million). Expected to run through 2029.
  • Segment 4 — Gila River bridges to Gas Line Road: A 3-mile connector between segments 1 and 3. Expected to start in 2027 or early 2028, with a completion date of late 2029.

Aerial view of a busy multi-lane freeway interchange with an overpass bridge crossing the highway, surrounded by arid Sonoran desert scrubland, with heavy vehicle traffic including trucks and cars visible in both directions.

A freeway interchange along the I-10 Wild Horse Pass corridor, where three existing interchanges are being fully reconstructed as part of segment 3. (InsideTheValley.com)

Aerial view of a multi-lane divided highway under active widening construction in an arid desert landscape, with a yellow crane between highway spans and traffic moving along existing lanes.

Segment 4 start date — and what has to happen before the full corridor is done

Segment 4 is a 3-mile connector. It links the Gila River bridge work to the Gas Line Road area, filling the gap between segments 1 and 3. ADOT spokeswoman Marcy McMacken said it is expected to start in 2027 or early 2028. All four segments should be finished by late 2029.

Segment 3 runs the longest and costs the most. Until it is done, plan for construction on the stretch of I-10 closest to Chandler and Ahwatukee every time you head south.

Common questions

When will the I-10 widening between Phoenix and Casa Grande be finished?

ADOT expects the entire 26-mile I-10 Wild Horse Pass Corridor Project to be complete by late 2029. Segment 3 — the 11-mile stretch between Loop 202 and the Gila River — runs through 2029. Segment 4, the final piece, is expected to start in 2027 or early 2028 and also finish by late 2029.

What exactly are they building on I-10 south of Chandler?

Crews are adding a third general-purpose lane in both directions across 11 miles between Loop 202 and the Gila River. They are also adding HOV lanes in both directions between Loop 202 and Riggs Road, reconstructing three interchanges (Wild Horse Pass Boulevard, Riggs Road, and Queen Creek Road/SR 347), building a brand-new interchange at Koli Road, replacing asphalt with concrete pavement, and installing overhead messaging boards, freeway cameras, and wrong-way detection systems.

Will there be HOV lanes on I-10 south of Loop 202?

Yes, but only on part of the segment. HOV lanes are being added in both directions between Loop 202 and Riggs Road. They are not extending the full 11 miles to the Gila River.

Who is the contractor building the I-10 widening near Chandler?

The design-build team for segment 3 is the Coffman-Fisher joint venture, made up of Coffman Specialties, Inc., Fisher Sand & Gravel Company, and lead designer Stantec Consulting Services Inc. ADOT selected this team for the $410 million segment.

What is the Koli Road interchange on I-10?

The Koli Road interchange is a brand-new freeway interchange being built as part of segment 3. It is not a reconstruction of an existing interchange — no interchange exists at Koli Road today. It will sit between Wild Horse Pass Boulevard and Queen Creek Road/SR 347 on I-10.

How many segments is the I-10 Wild Horse Pass Corridor Project?

Four segments cover the full 26-mile corridor from Loop 202 in south Phoenix to SR 387 near Casa Grande. Segment 1 (Gila River bridges) started in May 2024. Segment 2 (near Casa Grande) started in January 2026. Segment 3 (Loop 202 to Gila River) started in October 2026. Segment 4 (Gila River to Gas Line Road) is expected to start in 2027 or early 2028.

How much does the I-10 Wild Horse Pass Corridor Project cost?

The overall program is nearly $1 billion. Segment 3 alone — the 11-mile stretch between Loop 202 and the Gila River — carries an estimated cost of $410 million. Segment 1, the Gila River bridge replacement, was awarded for $71.2 million.

Will the I-10 widening affect my commute from Queen Creek or Ahwatukee to Phoenix?

Yes. Segment 3 covers the portion of I-10 closest to those communities. Expect lane closures, shifted traffic patterns near the Loop 202 and Riggs Road interchanges, and active work at four interchanges through 2029. The Queen Creek Road/SR 347 interchange is one of three being fully reconstructed, and a new Koli Road interchange is being built nearby.

Aaron Dotterer
Aaron Dotterer
REALTOR® · Dott Real Estate Group, Real Broker

Firefighter-EMT and licensed REALTOR® living in Eastmark. I cover what actually changes for residents when the Valley builds.

Book a strategy call
★★★★★
He was patient and understanding and never pressured us into a house or area. He listened to us as we explained our needs and wants…
— Maggie
★★★★★
Aaron was very helpful and supportive when it came to finding a home. He was quick to respond and was ready to help wherever he could…
— Amanda
★★★★★
Responsive, organized, and never made us feel like just another transaction. Highly recommend.
— John

Sources

↑