Yes, construction at Phoenix Sky Harbor International Airport’s west entrance is active this Thanksgiving week. A lane reduction on the approach road was in place through Nov. 21. Officials opened two lanes and paused work starting Nov. 22, running through Nov. 30 — but the project resumes after that, and road changes will continue into 2027.
Your drive to Sky Harbor just got more complicated — here’s how
If you are dropping someone off or picking them up at the west side of Sky Harbor this week, the worst of the squeeze is behind you for now. The one-lane restriction that had been slowing traffic on the west entrance approach was in place through Saturday, Nov. 21. Construction paused on Nov. 22 and two lanes reopened for the holiday window.
That pause runs through Nov. 30. After that, work picks back up — and so does the lane pinch. The two heaviest return-travel days at PHX are Sunday, Nov. 29 and Monday, Nov. 30. TSA projects more than 78,000 passengers screened on Nov. 29 and another 71,000 on Nov. 30. Construction restarts the following Monday, right after that peak fades.
If you are heading to Terminal 3 specifically, keep in mind that eastbound Sky Harbor Boulevard on the north side of Terminal 3 was closed nightly from 10 p.m. to 6 a.m., Nov. 9 through Nov. 19 (except Friday and Saturday nights), with traffic detoured through Terminal 3’s Inner Curb lanes. That overnight closure schedule has ended, but the broader roadwork continues.
Build in extra buffer for parking and check-in regardless. TSA recommends arriving at least two hours before a domestic flight and three hours before an international one during the holiday period.

The west entrance to Phoenix Sky Harbor International Airport, where Taxiway U construction has narrowed traffic to one lane in recent weeks. Work pauses Nov. 22–30 for Thanksgiving. (InsideTheValley.com)
What is Taxiway U and why is Sky Harbor building a $332.9 million bridge?
The project is called Taxiway U — also known as Taxiway Uniform. It is a roughly 2,060-foot elevated bridge being built at the western end of the airport. When finished, it will connect the north and south airfields with a crossfield taxiway for the first time on the west side.
Right now, Phoenix Sky Harbor has three crossfield taxiways. All three are on the east end of the airfield. Taxiway U will be the first crossfield taxiway on the west end — a new capability, not just a duplicate of what already exists on the other side.
The project has roots in Sky Harbor’s Comprehensive Asset Management Plan, first laid out in 2019 and updated in 2022. It is not a new idea that sprang up overnight.
The total project budget is $332.9 million. The construction budget sits at $279.5 million. In January 2025, the project received an additional $84.3 million in federal funding. The project also involves roadway realignment and utility relocation, with the initial phase including modifications to both Sky Harbor Boulevard and Buckeye Road.
How far along is the project — and what road changes are still ahead?
As of September 2026, the Taxiway U project had passed the 55% completion mark. Two of the three bridge spans are finished. The final span is scheduled for completion by summer 2027.
This fall, eastbound Sky Harbor Boulevard traffic from Interstate 10 shifted below the new bridge as its final new alignment. Buckeye Road is also moving below the bridge in the same construction phase. Westbound Sky Harbor Boulevard is set to shift below the bridge by late spring 2027.
That means if you drive the west airport approach regularly — not just for Thanksgiving, but for work or errands near the airport — you will see the road layout continue to change well into next year.

Nighttime construction lane restrictions like those near Sky Harbor’s west entrance are part of the Taxiway U project, which continues through 2027. (InsideTheValley.com)
How many Arizonans are traveling this Thanksgiving?
AAA expects 1.7 million Arizonans to travel for Thanksgiving this year. About 1.5 million of them are driving. More than 100,000 are flying. Sky Harbor officials have said the day before Thanksgiving is historically one of the busiest travel days of the year at the airport, with the Sunday and Monday after being the heaviest return-travel times.
That tracks with the TSA numbers: more than 78,000 passengers projected for Nov. 29 and 71,000 more on Nov. 30. Construction resumes the Monday after those peaks — meaning the lane restriction returns just as the final wave of returning travelers is clearing out.
Tools that can help you move faster through the airport
Sky Harbor offers a free program called PHX RESERVE. It lets you book a TSA security checkpoint time at Terminal 4 (expanded as of July 2026) or Terminal 3. You can reserve a slot anywhere from one hour to six days before your flight. If you have not used it before, the holiday period is a good time to try it.
TSA still recommends arriving at least two hours early for domestic flights and three hours early for international ones, even with a reserved slot. Factor in the extra drive time if you are coming through the west entrance.
If you are looking for an alternative airport for future trips, see our guide to Mesa Gateway Airport restaurants, hotels, and parking in 2026. And for a look at what is coming to Sky Harbor beyond the bridge project, check out seven new routes added for 2026–2027.
When construction restarts — and what comes after Dec. 1
Work pauses from Nov. 22 through Nov. 30. It resumes the following Monday. At that point, the lane restriction on the west entrance approach returns. The final bridge span is due by summer 2027. Westbound Sky Harbor Boulevard is set to shift below the bridge by late spring 2027.
Until both of those milestones land, the west entrance to Sky Harbor will keep changing. If you use that approach often, plan for a longer drive time through at least mid-2027. The airport has not announced a full project completion date beyond the summer 2027 span milestone.
For a broader look at Phoenix-area road projects running through 2027, see our coverage of the Phoenix Mini Stack I-10 improvements and ADOT’s Thanksgiving 2026 freeway status.